Real Clean Coal: Japan’s Unit #2 Isogo Plant

By Robert Peltier -- November 4, 2010

I’m often asked: what is the cleanest coal-fired power plant in the world?  I am also asked: how “clean” is clean coal?

If emissions levels from a gas-fired combined cycle plant are the measure of “clean,” then there are emissions control technologies available today for coal-fired plants that can produce comparable emissions. To be sure, low emissions from coal-fired plants isn’t a technology problem, it’s a political problem.

Unit 2 at J-POWER’s Isogo Thermal Power Station is an exemplar for low emission coal-fired plants. The second unit at the plant entered commercial service in July 2009, so the plant has been in operation for about 18 months. The 600-MW ultrasupercritical unit 2 joins an earlier, similar plant built in 2002. Together, these two new plants replaced 1960s-vintage coal-fired plants and doubled power generation from the small project site. In addition, the new unit improves the plant’s gross thermal efficiency to about 45%, while reducing air emis­sions to those of a gas-fired combined-cycle plant.

This technology, the real deal, is available today for “repowering” existing coal plants. If the future belongs to the efficient, coal is very much still in the game.

Background

J-POWER was established as a whole-power generator and wires com by the Japanese government in 1952 and was privatized in 2004. Today, J-POWER is owned by Electric Power Development Co., Ltd. (EPDC), which continues to distribute wholesale energy from principally hydroelectric and fossil-fueled plants to 10 utilities located across Japan.

The original Isogo Thermal Power Station (Isogo) consisted of two coal-fired units, each rated at 265 MW, that began commercial operation in 1967 and 1969. After 35 years of service, J-POWER elected to repower the plant, which is located on a peninsula in Yokohama Harbor. The project had three goals: The new plant was to lower emissions levels to those of a gas-fired plant, increase the amount of electricity produced for Japan’s second largest city, and improve the plant’s oper­ating efficiency (Figure 1).

isogo power plant

1. The Isogo Power Plant. Courtesy: J-POWER

Build, Scrap, Build

Development of the new facilities on a tight 30-acre site used what EPDC called the “build, scrap, build” approach. First, the new 600-MW Unit 1 was built; then the older two units were shut down and scrapped to free up precious land; then the new 600-MW Unit 2 was built. This approach also ensured that the new Unit 1 re­liably replaced the energy produced by the old plant before decommissioning.

Construction of the new Isogo Unit 1 began in 1998, and commercial operations followed in April 2002. The two older units were decommissioned in November 2001, and the project site was “scrapped” by March 2004. Construction of the new Unit 2 began in October 2005, and it en­tered commercial service in July 2009.

When Isogo Unit 2 entered commer­cial service, power generating capacity was more than double what had been pro­duced by the original plant. In addition to meeting Yokohama’s generation needs, Isogo was designed for maximum thermal efficiency.

High efficiency requires high steam pressures and temperatures. The main steam pressure is ultrasupercritical (USC) at 25 MPa (3,626 psi) with a main steam temperature of 600C (1,112F). Reheat is a blistering 620C (1,148F). Unit 1 operates with the same steam conditions, except the reheat temperature is just 10C less, at 610C. The gross thermal efficiency of the new Unit 2 is 45% (LHV).

Clean Sweep

Isogo ranks as the cleanest coal-fired pow­er plant in the world in terms of emissions intensity, with levels comparable to those from a natural gas–fired combined-cycle plant. The air quality control system on Unit 2 is a multipollutant control system, unlike the individual components found on Unit 1 and on most coal-fired plants. Unit 2 uses a unique regenerative activated coke dry-type technology (ReACT) that scrubs SOx from the flue gas but also removes mercury and NOx as a co-benefit (Figure 2). A thorough discussion of this new mul­tipollutant control technology appeared in “ReACT Reduces Emissions and Water Use” in the July issue of POWER available here)

isogo power plant

2. In the ReACT multipollutant control system, flue gas passes through activated carbon in the desulfurization tower to adsorb sulfur ox­ides. Spent activated carbon is sent to the regeneration tower, where the SO2 is re­moved and the activated carbon is reused. The SO2 is recovered as a highly concen­trated sulfuric acid that has market value. As a co-benefit, 20% to 40% of the NOx and up to 90% of both elemental and oxidized forms of mercury are removed in the pro­cess. Courtesy: J-POWER

Another very important advantage for the ReACT technology is that it uses only 1% of the water required by conventional wet flue gas desulfurization systems.

The low levels of air emissions reached by Isogo Unit 2 are, quite frankly, phenom­enal and set a new standard for coal-fired power plant design (Figure 3 illustrates the comparison with existing plants). These numbers should interest plant designers and regulators alike:

· Flue gas emissions are first treated by an ammonia selective catalytic reduction de-NOx system before entering the ReACT system. Together, they reduce NOx from 159 ppm to an average of about 16.5 ppm (13 ppm is the permit level for Unit 2). However, operating experience has found that the plant typically operates in the single-digit ppm levels. This equates to an overall NOx removal rate of about 92%.

· ReACT reduces SOx from 60 ppm to an average of 15 ppm (10 ppm is the per­mit level for Unit 2). Unit 2 regularly operates with single-digit ppm levels of SO2, reflecting an almost 98% rate of reduction.

· ReACT removes up to 90% of both elemental and oxidized forms of mer­cury through adsorption using activated coke.

· By using an electrostatic precipitator, soot and dust emissions were reduced from 50 mg/Nm3 to an average of 7.5 mg/Nm3, and Unit 2 operates at less than 5 mg/Nm3 or 0.005 lb/mmBtu). This performance equates to over 99.9% re­moval efficiency. The flue gases are then exhausted to the atmosphere through a common 200-m stack.

· The improved plant thermal efficiency reduced the amount of CO2 released into the atmosphere by 17% on a lb/ kWh basis. J-POWER understands that reducing CO2 reductions from coal-fired plants begins by designing a plant with the highest possible thermal efficiency.

isogo environment footprint

3. Small environmental footprint. ReACT is a regenerative activated coke–based technology that produces saleable by-products (sulfuric acid or gypsum) and, as a dry process, does not require water. The technology should be of special interest to U.S. utilities burning lower-sulfur western fuels, especially at locations where there are significant water supply concerns. J-POWER reports that SO2 and NOx emissions at the Isogo plant are both at single-digit ppm concentration levels—emissions that are on par with a natural gas–fired plant. Data for Japan represent combined data for Japan’s 10 regional electric utilities and J-POWER. Figures for Isogo represent actual performance for fiscal 2008. Country figures represent combined emissions intensity for coal-, oil-, and gas-fired thermal power plants. Source: Federation of Electric Power Companies of Japan

Strong Market Plan

Demonstrated single-digit levels of emis­sions could have a profound impact on future permitting of coal-fired plants worldwide, especially in the U.S. Certain­ly, constructing a similar plant in the U.S. would set the benchmark for emissions permits for future coal-fired plants.

J-POWER has also announced that “preparations for environmental impact assessment” have begun for replacement of the two units at the Takehara Thermal Power Station. This 1,300-MW station, built in 1967 and 1974, would remain in service during construction of two like-sized, but much more efficient units with much lower emissions. The two older units would be retired after construction is com­pleted in 2020. Construction is estimated to begin in 2014.

-Portions of this article appeared in POWER magazine

7 Comments


  1. Jon Boone  

    Another important post about a significant development. Thanks, Bob. Are there figures available about the capital and projected operating costs, particularly compared to the costs of a combined cycle natural gas facility?

    Reply

  2. JavalinaTex  

    Thank you for the article Dr. Peltier

    A few comments and a question:

    First, it would be instructive to have an “emissions” inventory of the current criteria pollutants for this sort of facility in units that are used in the US. My math says 0.2 g/Kw-Hr would equate to 215 Short Tons/Year. PM 10 and 2.5 are not addressed, either. Also, the graph is confusing in that it shows Isogo to be lower in emissions than “Japan” while being labeled as having higher specific emissions (indicated 0.3 g/Kw-Hr SO2 and 0.7 g/Kw-Hr NOx vs 0.2 g/Kw-Hr each for SO2 and NOx).

    Second, it would be helpful to see these emissions and heat rate for Natural Gas Combined Cycle and Integrated (Coal) Gasification Combined Cycle plants.

    In my mind, having found the lack of interest in Ultra Super Critical plants (I have discussed this off the record with a former employer/developer as to why they were building a Super Critical plant in stead of a USC plant) puzzling. Hence, the real instructive question for anyone interested in public policy is the following:

    “What is it about the US economic and environmental regulatory structure and industry financial structure that results in the United States running a fleet of old coal plants with high heat rates?”

    I have long subscribed to Power (despite spending my 30 year career in the Natural Gas Industry) and have enjoyed the many informative articles.

    Reply

  3. JavalinaTex  

    P.S. – the conversion to ST/Y assumed 600 MW capacity and a 90% annual load factor. Typically, one might have two or three of these units at a station (1,800 MW) so for the site the number would b tripled if you built 3 state of the art units. Obviously at most sites one would likely exceed PSD permit levels even in one was in an attainment area.

    Reply

  4. Donald Hertzmark  

    Javelina,
    I think that the point of this post is that replacing an old plant with a new USC plant will reduce fuel use, emissions and improve both availability and capacity factor significantly. Therefore, the proper comparison is a with and without the USC units replacing older units. In that case there is an unambiguous improvement in air quality, fuel consumption and plant availability. All to the good, as I see it.

    Reply

  5. Breaking Wind – Quick hits from the industry for November 5, 2010 « Allegheny Treasures  

    […] Real Clean Coal: Japan’s Unit #2 Isogo Plant – MasterResource […]

    Reply

  6. Paul in Sweden  

    This technology is very interesting but what are the associated and comparative costs of building and operating a USC plant?

    Reply

  7. Daniel Tambing  

    INDONESIA COAL OPEN SALES
    Dear,
    JAPAN COAL POWER PLANTS

    I’m Daniel Tambing, Indonesia. I’m collaboration with many of direct miner’s, confirmed with SOFT CORPORATE OFFER responsibility, that I’m ready and capable to enter into a contract to sell the commodity, with the following terms, conditions and specifications as stated below. The sales and purchase contract would be in accordance with international standard and procedures willing and able to enter into contractual agreement with the buyer for the sales of the following commodity. Please send your official LOI (Letter of Intent) and let us know the details specification before making any negotiations. Ready 50,000 to 200,000 MT/Month in various spec in best quality and best price (negotiable).
    Please send your official LOI (Letter of Intent) and let us know the details specification before making any negotiations.

    Please find the following coal offering with details term and condition asf :

    1. GAR 42

    Analysis Typical Rejection Limit
    GCV (arb) 4.100 kcal/kg 0.6 %
    Ash (adb) 6.00 % >8.00 %
    VM (adb) 40 % approx –
    Sizing (0-50mm) 85 % min –
    HGI 60 –

    Terms as follows:
    • Price: US$ 33 /MT FOB MV Geared and Grab Muara Asam-Asam Anchorage
    with load rate 8000mt/days pwwdshinc (full Export Document)
    • Quantity: 50,000 MT +/- 10%
    • Payment basis: 100% by irrevocable LC at sight. Terms include: T/T reimbursement
    allowed 3 business days after full documents are submitted to advising bank and
    transmitted to issuing bank along AWB details.
    • Laycan: Through July 2015 (to be mutually agreed), first day of MV laycan to be 10
    calendar days after workable LC is received by beneficiary’s bank.
    • Our draft contract with full specifications and LC format is available upon request
    with only minor terms and conditions negotiable where necessary.‎
    • Validity: July 31, 2015
    2.
    GAR 6000 (reject 5800) coal from Central Kalimantan.

    OFFERED QUANTITY : 45,000 MT +/- 10% MOLO
    FOB PRICE : US$58 PMT FOB Geared Vessel (Full Export Document)
    DELIVERY : Through July, 2015
    PAYMENT TERM : by Letter of Credit (L/C) payable at Sight for 100% shipment value
    LOADING PORT : Mother Vessel Anchorage at Taboneo, South Kalimantan
    LOADING RATE : 8,000 MT PWWDSHINC
    INSPECTION : Quantity, Quality, and Weight by independent surveyor at loading port
    PACKAGING : Bulk (by Geared vessel)
    OFFER VALIDITY : 5 Days

    Enclosed our ET Cerft, Company profile and previous COA for your kind reference.

    We’re looking forward to hearing a good news soon.

    Thank you and Best regards

    Daniel Tambing, marketing

    PASIFIK GROUP INDONESIA
    CBD Pluit, The Honey Lady Tower,11th Floor, Jl. Pluit Selatan Raya No.18
    North Jakarta 14440, Indonesia,
    Phone +62 813 7255 9088/ +62 813 7255 9099/ +62 812 9359 6132
    Skype : daniel.tambing
    BlackBerry Pin. 532F9A28
    e-mail. property_penta@yahoo.com

    *) Also available other Coal types : (direct miner’s)

    Reply

Leave a Reply