A Free-Market Energy Blog

Anti-Nuclear Group Uses Free Market Arguments against Vogtle Plant

By Jim Clarkson -- December 8, 2015

“In an unregulated market, Georgia Power’s profits would be linked to its performance. It is only through the PSC’s authorization that Georgia Power has posted such large profits for its shareholders at the expense of the Georgia ratepaying public.”

Defenders of consumer choice and free markets rarely pay attention to the technical criticisms of nuclear generation by the often hysterical opponents of nuclear power. Therefore, it is a pleasant surprise to see sensible reasoning used to oppose the spread of this cost-prohibitive, subsidized source of electrical generation.

In Georgia, the utility and its regulators have heard the charges shown below and ignored them, likely because the facts cited cannot be refuted.

Here, in its entirety, is pre-filed testimony by Nuclear Watch South in question-and-answer format. 

DIRECT TESTIMONY AND EXHIBITS OF GLENN CARROLL ON BEHALF OF  NUCLEAR WATCH SOUTH

Part I: INTRODUCTION

Please state your name, profession, and business location.

My name is Glenn Carroll. I am coordinator of Nuclear Watch South. My business address is P.O. Box 8574, Atlanta, Georgia 31106.

 Ms. Carroll, please summarize your educational and professional experience.

I am coordinator of Nuclear Watch South and have 28 years experience with nuclear issues. My resume was submitted to the public record in the 12th Vogtle Construction Monitoring Review (VCMR). Besides experience with multiple pro se legal interventions before the U.S. Nuclear Regulatory Commission’s Atomic Safety & Licensing Board, I provided testimony before the Georgia Pubic Service Commission in the preceding 12th VCMR. In addition to ongoing involvement with the VCMR process, I am a veteran eyewitness to the Vogtle I & II prudency hearings and rate cases in 1987 and 1988. The information I present is publicly available information which is accessible and understandable to all Georgia citizens.

 On whose behalf are you testifying in the 13th Semi-Annual Vogtle Construction Review

Georgia members of grassroots consumer group Nuclear Watch South.

 What are the issues in this case?

To examine, in accordance with O.C.G.A. § 46-3A-7(b), the ongoing necessity and public convenience of expanding Georgia Power’s electric generating capacity, especially with respect to continuing to construct unneeded power supply at Vogtle. 

What is the purpose of your testimony?

To present factual evidence proving that Plant Vogtle expansion is not needed in support of Commission action to revoke certification of Vogtle 3 & 4 construction in accordance with its legal authority to provide Georgia electricity customers safe, reliable and reasonably priced electric services. 

What information sources do you rely upon in your testimony?

Georgia Power data obtained from Georgia Power 2004-2014 annual reports and Official Code of Georgia Annotated.

Part II: VOGTLE 3 & 4 ARE NOT NEEDED

Please explain the updated chart titled Georgia Power Key Financial & Operating Data (Exhibit #1)

The updated chart consists of eleven (11) years of Georgia Power annual report data from the period 2004-2014. As explained before in the 12th VCM, line 3 shows that Georgia Power’s sales volume is flat for the period and line 6 shows Georgia Power’s capacity utilization has declined from 72% to 58% for the same period. Vogtle 3 & 4 were certified based on Georgia Power’s forecasts of 4.1% annual growth which has not happened, as shown by the data. Electrical power from Vogtle 3 & 4 are simply not needed. (see Exhibit #2, Georgia Power Sales Volume 2004-2014, updated 11/15)

How has the chart changed from the 12th VCM?

The chart has been amended from the 12th VCM to include Georgia Power’s net income (profits).

 What does the chart show about Georgia Power’s profits?

Line 2 of the updated chart shows that Georgia Power’s profits have increased more than 80% in the 10 year period 2004–2014. For the same period, overall electricity sales fell .4% (line 3).

Notably, Georgia Power profits jumped by 11.5% with the beginning of collection of the Construction Work in Progress (CWIP) tariff AKA Nuclear Construction Cost Recovery (NCCR) in 2011 and the CWIP years 2011–2014 stand out for posting consistent $1 billion plus annual profits.

Georgia citizens did not fare as well as Georgia Power which profited also from raising the price of electricity for Georgia Power’s residential customers by more than 18% between 2010 to 2014 as shown on Line 4.

The NCCR tariff also increased by 65% from 2011-2014.  (See Exhibit #3: Nuclear Cost Recovery Rider Collections from 2011 through 2016, Docket #32539, Docs #133156, 139740, 145298, 152092, 156291)

Neither Georgia Power, the Public Interest Advocacy staff nor the PSC have refuted Nuclear Watch South’s assertion that Vogtle 3&4 are not needed.

In an unregulated market, Georgia Power’s profits would be linked to its performance. It is only through the PSC’s authorization that Georgia Power has posted such large profits for its shareholders at the expense of the Georgia ratepaying public.

PART III. PUBLIC SERVICE COMMISSION

What is authority and responsibility of the Georgia PSC in regulating the Vogtle expansion project?

Georgia Public Service Commission’s website states: “The mission of the Georgia Public Service Commission is to exercise its authority and influence to ensure that consumers receive safe, reliable and reasonably priced telecommunications, electric and natural gas services from financially viable and technically competent companies.”

State of Georgia Rules and Regulations (515-2-1-.01) says:

Every member of the Commission will, in all cases, reserve his opinion and in no way commit himself in advance touching the merits of any matter or question to be passed upon by the Commission or that should be dealt with by it, until the facts and evidence are all submitted and the Commission considers the same in administrative session.

In determining findings of fact or in its deliberations, the Commission will hold no presumption in favor of the position of any party, including the Public Interest Advocacy Staff, and shall only give weight and credit to any party in the case as can be supported by credible evidence in the record. Rule 515-2-1-.01 “Opinions of Commissioners”

Georgia Code O.C.G.A. § 46-3A-6 “Reexamination of a certificate of public convenience and necessity; modification or revocation” states that

“Upon … its own motion, the commission may reexamine any certificate … to determine whether … future requirements require the modification of the construction … or expenditure for a certificated capacity resource.”[1]

Taken together, the three statutes quoted from Georgia law give the PSC the responsibility to ensure Georgia consumers reliable electricity at reasonable rates, the mandate to weigh all the evidence before issuing an opinion, and the authority to revoke the certificate of a resource that does not meet the necessity test.

As we have already shown in Section II, Georgia Power is presenting a large percentage of unused existing capacity while experiencing flat market conditions. Vogtle 3 & 4 are simply not needed. Furthermore, Georgia Power is enjoying an average 6.0% annual net income increase amidst slack sales even as the Vogtle project falls egregiously behind schedule and goes over budget. It is not fair for Georgia citizens to enrich Georgia Power for a mismanaged construction project, a project that is not even needed.

Nuclear Watch South urgently calls upon the  Commission to exercise the responsibility and authority vested in it by Georgia O.C.G.A. § 46-3A-6 to revoke Vogtle certification. The PSC needs to act immediately as the Vogtle expansion project falls behind at the rate of almost a day for every single day it is under construction, and the sunk costs mount by millions of dollars each month, costs which the public, not Georgia Power, has been forced to pay.

PART IV: GEORGIA RATEPAYERS WOULD BENEFIT MORE FROM CANCELLING CONSTRUCTION THAN COMPLETING VOGTLE 3&4

Q. Would it be more beneficial for Georgia Power customers to finish Plant Vogtle 3&4 or to cancel construction

It would be cheaper to cancel construction given that Plant Vogtle 3&4 are not needed. Georgia Power testified in the current 13th VCMR that Vogtle expansion is still only 25% finished. Georgia Power and its partners have spent almost $6 billion on Vogtle so far (and as has been well publicized, are $2 billion over budget and three years behind schedule). The cost of the completed project is roughly $18 billion at present. The cost to cancel the construction project would be far less than the $12 billion left to be spent.

Georgia Power is protected from financial risk from cancelling Vogtle expansion by the Georgia Code O.C.G.A. § 46-3A-6 which allows Georgia Power to recover the cost of shutting down the unneeded power plant construction.

 PART V.   CONCLUSIONS &  RECOMMENDATIONS

 Q. Please summarize your conclusions & recommendations for the Commission.

 Conclusions:

The Georgia Public Service Commission’s (PSC) mission is to “exercise its authority and influence to ensure that consumers receive safe, reliable and reasonably priced … electric service.”

The PSC has the authority to cancel Vogtle 3&4 reactors at any time if the certified capacity is no longer needed.

Georgia Power annual report data reveals that the company is overbuilt in a shrinking, shifting market and no longer needs the power from Vogtle 3&4.

Georgia citizens are paying an unprecedented nuclear tariff for Vogtle construction which is resulting in unprecedented profit increases for Georgia Power.

The greatest benefit to the Georgia public since Vogtle 3 & 4 no longer meet the necessity test is for the Commission to immediately revoke certification and stop billing Georgia electric customers. 

Recommendation

The Georgia Public Service Commission should revoke certification for Vogtle 3 & 4 in order to protect Georgia electricity customers from further investment in an unneeded power source.

——————

[1] [Georgia Code O.C.G.A. § 46-3A-6]:

Upon application of a utility or upon its own motion, the commission may reexamine any certificate granted under this chapter to determine whether new forecasts of future requirements require the modification of the construction, purchase, sale, or expenditure for a certificated capacity resource. If upon such reexamination the commission finds that the certificated capacity resource is no longer needed or that any additional certificated capacity resource is needed to assure a reliable supply of electric power and energy for the utility’s Georgia retail customers, the commission may modify or revoke the certificate.

If the utility cancels, abandons, or increases some or all of the capacity resource as a result of such modification or revocation of the certificate, it may recover through any rate-making vehicle over a reasonable period of time, absent fraud, concealment, failure to disclose a material fact, imprudence, or criminal misconduct, the amount of its investment in such capacity resource, along with the cost of carrying the unamortized portion of that investment, net of actual salvage value, to the extent such investment is verified as made pursuant to the certificate. The commission shall disallow such investment and costs resulting from fraud, concealment, failure to disclose a material fact, imprudence, or criminal misconduct. [emphasis added]

Leave a Reply